Construction and exploatation of new objects ensure multimillion incomes to local community
At the International economic forum „ Corporative management in BiH - How and where next „ ( Dubrovnik ; 5-6.December 2013)), dr.Elvedin Grabovica, General manager of JP Elektroprivreda BiH, discussed on topic ¨Impacts of construction of new energo facilities to the development of local community „ Dr Grabovica has presented concept of development of energo facilities of JP Elektroprivreda BiH and some analyses of accompanying effects during period of construction and usage of generation capacities.
The backbone of the investment cycle in JP Elektroprivreda BiH include capital projects as :
- Unit 7at TPP ¨Tuzla¨, power 450 MW, anual generation 2700 GWh, construction period from 2014 - 2018.
- HPP ¨Vranduk¨, power 20 MW, anual generation 96 GWh, construction period from 2014 - 2018.
- Wind power plant „Podveležje“, power 48 MW, anual generation 103 GWh, period of construction 2014 - 2016.
The construction and exploatation of the objects of Elektroprivreda BiH will ensure multimillion incomes to local community . Refering to that segment the most significant period is exploatation period which will ensure direct incomes from materials , fees to the municipalities where are placed the facilities for generation of JP Elektroprivreda BiH, the charges , taxation and employment , standard improvement and development of local companies . Besides some direct financing effects refering to the construction / various charges , taxes , employers' earnings , domestic rows / , there are other potential benefits and chances for development of national economy and local community .